Development envelope

Gross floor area (GFA)62,500sqft
Modeled saleable area47,500sqft
Land price per plot sqftAED 1,400
Land price per GFA sqftAED 560

05

Evidence register

These notes remain on this device and are never added to the enquiry or shared link.

06

Three-scenario feasibility

Downside

-AED 13,989,375
Gross development value
AED 76,950,000
Total development cost
AED 90,939,375
Profit on cost
-15.4%
Margin on revenue
-18.2%
Construction
AED 37,812,500
Finance cost
AED 6,451,250

Base

-AED 1,523,250
Gross development value
AED 85,500,000
Total development cost
AED 87,023,250
Profit on cost
-1.8%
Margin on revenue
-1.8%
Construction
AED 34,375,000
Finance cost
AED 6,129,500

Upside

AED 10,942,875
Gross development value
AED 94,050,000
Total development cost
AED 83,107,125
Profit on cost
13.2%
Margin on revenue
11.6%
Construction
AED 30,937,500
Finance cost
AED 5,807,750

07

Price and residual signals

Break-even selling priceAED 1,834sqft
Residual land value at target returnAED 20,956,86420% Profit on cost
Residual land value per plot sqftAED 838sqft
Simple annualized project return-0.6%A timing simplification—not IRR

The numerical case and evidence notes are saved separately on this device. No confidential deal document or identity is sent.

The Legends review

Move from preliminary feasibility to verified land due diligence.

Only the published reference and a short numerical summary carry into the enquiry. Evidence notes and the complete local model never leave this device automatically.

Build the land bid & payment terms
Request land review

Preliminary feasibility sensitivity only—not a valuation, planning confirmation, engineering study, quantity-surveyor estimate, financing offer, legal, tax or investment advice. FAR, permitted use, GFA/BUA treatment, exclusions, parking, efficiency, buildability, sales evidence, costs, phasing, finance and approvals must be verified with the relevant authority, master developer and qualified planning, engineering, QS, finance, legal and tax advisers. Simple annualized return is not IRR and ignores cash-draw timing.